BUS 799 Module 4 Capstone Findings Example

Reviewed by Douglas Renshaw, MBA Aspen University Updated October 2026

This BUS 799 Module 4 sample paper reports current-state findings for an MBA capstone at Keystone Electric, a composite electrical subcontractor whose owners want receivables cut from 71 days to 50. The fourth module of Aspen University's Graduate Capstone, an MBA course, asks for the analysis and findings. The decomposition of 1,146 payment applications reconciles to within 1.5 days of the measured total and shows that 12 days pass before Keystone even submits an application. Coding of 80 late invoices, with a kappa of 0.78 as Cohen's statistic measures, finds missing lien waivers and backup, late submission and unsigned change orders leading. The largest customer averages 84 days. Interviews analyzed with Braun and Clarke's method produce four themes. Retainage is examined separately, causes are sorted by how far Keystone controls them, about 19 days, and limits are stated.

CourseBUS 799 Graduate Capstone
ModuleModule 4
Paper typeCapstone findings
LengthAbout 1,000 words, 6 pages
FormatAPA 7 student paper
SchoolAspen University
ProgramMBA
UpdatedOctober 2026

Free sample paper for BUS 799 Module 4

1

Twelve Days Before We Even Ask: Current-State Findings on Where Keystone's Receivable Days Come From

Student Name

Master of Business Administration Program, Aspen University

BUS 799: Graduate Capstone

Instructor Name

Month Day, Year

What this page is doingThe title leads with the most actionable finding, the delay inside the company before billing, which is what the analysis most wants the owners to see. APA 7 student title page; the company and data are composite.
2

Twelve Days Before We Even Ask: Current-State Findings on Where Keystone's Receivable Days Come From

This section reports the current-state analysis for the capstone at Keystone Electric, where the owners want receivables cut from 71 days of sales to 50. Following the methodology, it presents the decomposition of days by stage, the results of coding the causes of 80 late invoices, differences among general contractors, and themes from twelve interviews, and then classifies causes by whether Keystone can control them.

What this page is doingThe introduction states what the section reports and ties it to the prior methodology.
3

Where the Days Go

The revenue-weighted decomposition of 1,146 payment applications reconciled to within 1.5 days of the measured 71. Table 1 shows the result.

StageDaysShare of 71
Billing lag: period end to submission12.017%
General contractor and owner review18.025%
Payment after approval22.031%
Rejected applications, added time3.55%
Unsigned change orders3.55%
Retainage held12.017%
Total71.0100%
What this page is doingThe decomposition is presented with its reconciliation check, so the reader can trust that the parts account for the whole.
4

What the Decomposition Shows

The most striking finding is that 12 days pass, on average, between the end of a billing period and the submission of Keystone's payment application. Before any customer has a chance to be slow, Keystone has already given away 12 days. Payment after approval, at 22 days, is the largest component, but it reflects general contractors' payment terms and their own receipt of funds from project owners, which Keystone cannot directly change. Retainage accounts for 12 days, because retainage from completed projects often remains unpaid for months while closeout documents are gathered. Rejections and unsigned change orders together add 7 days.

What this page is doingThe interpretation highlights the controllable finding first and explains each component's nature, which sets up the classification of causes.
5

Causes of Late Invoices

The author and the controller independently coded the primary cause of delay for 80 applications paid more than 60 days after the billing period ended. Agreement was substantial, with a kappa of 0.78 after the categories were refined in the pilot, above the 0.70 threshold set in advance (Cohen, 1960). The coded causes, from most to least frequent, were missing lien waivers or backup documents, 24 invoices or 30 percent; late submission, 19 or about 24 percent; unsigned change orders, 14 or about 18 percent; the general contractor awaiting payment from the owner, 11 or about 14 percent; retainage held, 6; arithmetic or format errors, 4; and disputed quantities, 2. The first three causes, all arising in Keystone's own processes, account for 57 invoices, or 71 percent of the sample.

What this page is doingThe coding results are reported with the reliability statistic against its threshold and ranked in Pareto order, showing that most causes are internal.
6

Differences Among General Contractors

Days outstanding varied by customer. The general contractor that accounts for 38 percent of Keystone's revenue averaged 84 days, while the second largest, at 22 percent of revenue, averaged 62. Rejections for missing lien waivers were concentrated with the largest customer, which requires conditional waivers from every lower-tier supplier with each application. This suggests that a checklist tailored to that customer's requirements could remove a large share of rejections.

What this page is doingSegmenting by customer reveals where the problem is concentrated and points to a targeted fix.
7

What People Said

Thematic analysis of the twelve interviews produced four themes (Braun & Clarke, 2006). First, billing competes with field work: project managers described preparing payment applications in the evenings after site duties, often days after the period ended. Second, no one owns the deadline: there is no firm cutoff date, and billing staff wait for project managers' quantities. Third, paperwork arrives late: lien waivers from suppliers and lower-tier subcontractors are requested only when the application is being assembled. Fourth, change work starts on a handshake: field crews begin extra work on verbal direction, and the signed change order follows weeks later, if at all. One general contractor's accounts payable specialist added that complete applications are approved in the first review batch, while incomplete ones wait for the next cycle, often two weeks later.

What this page is doingInterview themes are derived with a named method and directly explain the quantitative findings, including an external perspective.
8

Retainage in Detail

Retainage deserves separate attention because it behaves differently from progress billing. At the end of the period studied, Keystone held about $1.25 million in retainage receivables, equal to roughly 12 days of revenue. About 40 percent of that balance belonged to projects that had been substantially complete for more than 90 days. The records show why: final retainage is released only after closeout documents are delivered, including as-built drawings, warranties, operation manuals, and final lien waivers, and Keystone typically begins assembling these after the last day of field work. On two projects, retainage remained unpaid for more than six months because a single warranty letter from an equipment supplier was missing.

What this page is doingExamining retainage separately shows how one internal practice, late closeout preparation, keeps a large balance outstanding.
9

Which Causes Keystone Controls

The findings sort into three groups. Controllable: billing lag, missing documents that lead to rejection, and unsigned change orders, together worth about 19 days. Partly controllable: review time, which falls when applications arrive complete and on the general contractor's schedule, and retainage, which can be released sooner if closeout documents are prepared during the project rather than after it. Largely outside Keystone's control: payment after approval, which depends on contract terms and on owners paying general contractors. This pattern is consistent with the survey finding that construction payment problems stem partly from process shortcomings and disputes and partly from the financial position of other parties (Ramachandra & Rotimi, 2015).

What this page is doingCauses are classified by controllability, the key step toward recommendations, and the pattern is related back to the literature.
10

Limitations of the Findings

These findings have limits. The period studied included two unusually large hospital projects, which may overstate the influence of the largest general contractor. The cause coding assigned only a primary cause to each late invoice, although several invoices had more than one problem. Interviews with accounts payable staff at only two general contractors cannot show how every customer reviews applications. And the decomposition measures averages; individual projects vary widely. None of these limits changes the central conclusion, but they argue for testing recommendations on pilot projects before applying them company-wide.

What this page is doingStating the limits of the findings, and what they imply for the next step, shows mature judgment about the evidence.
11

Conclusion

Keystone's 71 days are not mainly a customer problem. About 19 days arise from its own billing lag, incomplete documentation, and unsigned change orders, and several more could be recovered through faster closeout and complete submissions. The next module develops a change and stakeholder plan to address these causes, focused first on the largest customer and on a firm billing cutoff. The owners reviewed these findings in a one-hour meeting and agreed that the billing cutoff and document checklist should be piloted first.

What this page is doingThe conclusion states the central finding and connects it to the next stage of the capstone.
12

References

Braun, V., & Clarke, V. (2006). Using thematic analysis in psychology. Qualitative Research in Psychology, 3(2), 77-101. https://doi.org/10.1191/1478088706qp063oa

Cohen, J. (1960). A coefficient of agreement for nominal scales. Educational and Psychological Measurement, 20(1), 37-46. https://doi.org/10.1177/001316446002000104

Ramachandra, T., & Rotimi, J. O. B. (2015). Causes of payment problems in the New Zealand construction industry. Construction Economics and Building, 15(1), 43-55. https://doi.org/10.5130/ajceb.v15i1.4214

Reading the BUS 799 Module 4 assignment instructions

In Aspen's BUS 799, Module 4 commonly asks for the current-state analysis and findings of your capstone. Present results in the order the methodology set. Show the main decomposition in a table and confirm it reconciles. State the most important finding plainly. Report coded causes with agreement statistics. Compare results across customers, units or groups. Summarize interview themes with short supporting quotations or paraphrases. Examine any component that behaves differently. Sort findings by what the organization controls. State limitations. Keep the organization composite and customers coded, and avoid recommending solutions here, since the next module is where recommendations are built from these findings.

How this BUS 799 Module 4 example is built

The introduction restates the target and the order of the findings. A table shows days by stage. The interpretation section highlights the 12-day billing lag before any customer delay. The causes section reports agreement after refining categories and ranks the primary causes of late invoices. The customer section compares the largest general contractor at 84 days with the second largest at 62 and notes where rejections cluster. The themes section reports four themes, starting with billing competing with field work. The retainage section examines about $1.25 million held, roughly 12 days of revenue. The control section sorts findings into controllable, partly controllable and outside Keystone's control. The limits section notes two large hospital projects, and the conclusion states that the 71 days are not mainly a customer problem.

Reading the BUS 799 Module 4 grading rubric

Findings papers in BUS 799 are graded on results presented in the planned order, accurate tables, reliability reporting, comparison across groups, integration of qualitative and quantitative data and honest limits. Because the six stages add back to within 1.5 days of the measured 71, graders can trust the arithmetic. Cohen's 1960 kappa supports the coding agreement, and Braun and Clarke's 2006 method supports the interview themes. Sorting causes by how far Keystone controls them prepares the recommendations. Stating that 19 days are within Keystone's control turns the analysis into a finding owners can act on. The limitations section names the two large projects that may skew results.

Common BUS 799 Module 4 mistakes, and how to avoid them

Findings papers often slide into recommending fixes. Hold those for the next module. Students also present a decomposition that does not add up; reconcile it. Students also report coded causes without agreement figures. Add kappa. Compare across customers or groups. Use interview themes to explain numbers. Treat special components, such as retainage, separately. Sort findings by control. State limits. Keep customers coded. Avoid blaming customers for delays your own process causes, and say how much of the total is truly theirs. Finally, put the single most important finding in one sentence near the top, since owners reading the report may stop after the first page.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official Aspen University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.

More BUS 799 and MBA sample papers

BUS 799 Module 4 questions, answered

What does BUS 799 Module 4 usually ask for?

Work in this part of a graduate business capstone often asks for the analysis and findings: what the data show about the problem and its causes. Aspen does not publish module deliverables, so your classroom's instructions govern.

What is a Pareto analysis in a capstone?

Ranking causes from most to least frequent to show that a few causes account for most of the problem, which tells you where to focus improvements.

How should capstone findings be reported?

Report what the data show with the checks you promised in your methodology, separate description from interpretation, and classify causes in a way that leads to recommendations.

Where can I find a free BUS 799 Module 4 sample paper?

The full BUS 799 Module 4 paper is above, reporting where a contractor's 71 days of receivables come from, with 12 days lost before it even bills.

Why does retainage get its own section in BUS 799 Module 4?

It behaves differently from progress billing. About $1.25 million, roughly 12 days of revenue, was held, and 40 percent sat on jobs finished more than 90 days earlier because closeout papers were gathered late.