MGT 474 Module 7 Monitoring With Earned Value Example

Reviewed by Douglas Renshaw, MBA Aspen University Updated October 2026

This MGT 474 Module 7 sample paper reports the status of the composite Wichita zoo's river otter exhibit 73 weeks after work began, using earned value management. Aspen University's Project Management course teaches how to tell whether a project is ahead, behind, over or under, and earned value answers all four with three numbers. At the end of June 2025, planned value was $1.01 million, earned value $930,000 and actual cost $1.02 million. The cost performance index of 0.91 forecasts a final cost of about $1.71 million against the $1.56 million base, and earned schedule forecasts finishing in mid-April 2026, using nearly two-thirds of the buffer. Fleming and Koppelman and the PMI standard explain the method, and Vanhoucke and Vandevoorde's simulations support earned schedule. Corrective actions protect the Memorial Day 2026 opening.

CourseMGT 474 Project Management
ModuleModule 7
Paper typeEarned value status report
LengthAbout 1,080 words, 6 pages
FormatAPA 7 student paper
SchoolAspen University
ProgramBusiness Administration
UpdatedOctober 2026

Free sample paper for MGT 474 Module 7

1

Ninety-One Cents of Work for Every Dollar: An Earned Value Status Report on a River Otter Exhibit 73 Weeks In

Student Name

Business Administration Program, Aspen University

MGT 474: Project Management

Instructor Name

Month Day, Year

What this page is doingThe title states the cost performance index in plain terms. APA 7 student title page.
2

Ninety-One Cents of Work for Every Dollar: An Earned Value Status Report on a River Otter Exhibit 73 Weeks In

Work on the otter exhibit at Meadowlark, a composite Wichita zoo, began in February 2024 from a base budget of $1.56 million, contingency of $290,000 and a 106-week critical path, leaving a 15-week buffer before the Memorial Day 2026 opening. At the end of June 2025, the 73rd week, the pool shell was finishing, the holding building was framed and the board asked for a status report. This report uses earned value management to answer whether the project is on schedule and on budget, and what will happen if nothing changes.

The Method

Fleming and Koppelman (2010) describe earned value as a way of measuring project performance by comparing three quantities. Planned value is what the work meant to be finished by a date was budgeted to cost. Earned value prices the work truly finished at those same budget rates. Actual cost is the money really spent on it. Comparing earned value with planned value shows schedule performance; comparing earned value with actual cost shows cost performance. The PMI standard defines these measures and the forecasts built from them (Project Management Institute, 2019). Earned value for each work package was measured by the percent complete agreed between the project manager and the contractor, using milestones such as poured walls and passed inspections.

Status 73 Weeks In

MeasureFormulaValue
Planned valueBudget for work scheduled$1,010,000
Earned valueBudget for work completed$930,000
Actual costSpent on work completed$1,020,000
Schedule varianceEV minus PV-$80,000
Cost varianceEV minus AC-$90,000
Schedule performance indexEV divided by PV0.92
Cost performance indexEV divided by AC0.91
Percent completeEV divided by base budget60%
Estimate at completion, CPI methodBase budget divided by CPIabout $1,711,000
Estimate at completion, CPI and SPI methodAC plus remaining work divided by CPI times SPIabout $1,770,000
What this page is doingFor every dollar spent, the project has completed about ninety-one cents of planned work.
3

Interpreting the Numbers

The project is behind schedule and over cost. It has completed $80,000 less work than planned and spent $90,000 more than the work completed was budgeted to cost. If cost performance continues at the current rate, the base work will cost about $1.71 million; if both cost and schedule pressures continue, about $1.77 million. In addition, $85,000 of contingency was drawn earlier for dewatering when groundwater appeared during excavation, a risk the register had anticipated. Adding that draw to the CPI forecast gives about $1.80 million, leaving roughly $55,000 of contingency within the $1.85 million budget, plus the board's $55,000 reserve. The project can still finish within budget, but the margin is thin.

Forecasting the Finish

Schedule variance in dollars becomes misleading late in a project, because it returns to zero when all work is done, however late. Vanhoucke and Vandevoorde (2007) used simulations of many project networks to compare methods for forecasting duration from earned value data and found that the earned schedule method generally gave the most reliable forecasts, especially later in projects. Earned schedule asks when the current earned value should have been reached under the plan. The plan reached $930,000 at the 67th week, so six weeks of schedule have been lost, and the time-based performance index is 67 divided by 73, or 0.92. Dividing the 106-week plan by 0.92 forecasts about 115 weeks, mid-April 2026. That uses about 9 of the 15 buffer weeks with 60% of the work complete, a warning sign but not yet a missed opening.

How Earned Value Was Measured

Earned value depends on honest measures of progress. Rather than asking the contractor for a general percent complete, which tends to run optimistic, the project manager credited work packages only at defined milestones. The pool shell, for example, earned 25% when excavation passed inspection, 50% when the floor was poured, 80% when the walls passed inspection and 100% when the waterproof coating was accepted. Small work packages were credited 0% until finished. These rules make the earned value figure harder to inflate and easier for the board to trust.

Reading the Indexes Together

The two indexes tell a consistent story. An SPI below 1.0 alone could mean work started late but is proceeding at normal cost; a CPI below 1.0 alone could mean higher prices on schedule. Both below 1.0 at once usually means rework or productivity problems, which is what the causes below confirm. A third measure, the to-complete performance index, shows that finishing within the $1.56 million base would require a CPI of about 1.17 on the remaining work, far better than achieved so far, so the base budget alone is no longer a realistic target and contingency must cover the difference.

Causes

Three causes explain most of the variance. A section of the pool wall failed inspection after a cold-weather pour and had to be removed and repoured, costing about $40,000 and three weeks. Rebar and steel prices rose after the contract's price adjustment clause took effect, adding about $30,000. The rockwork crew, a specialty subcontractor, worked more slowly than estimated on the curved pool edges.

Corrective Actions

The project manager recommends four actions. Rockwork will overlap with the start of water testing in sections not affected by the work, recovering about three weeks, with the veterinarian's agreement. Concrete pours will be scheduled only when forecast temperatures exceed 40 degrees, with heated blankets on standby. The contractor and project manager will review the remaining steel purchases to lock prices now. And the sponsor will be asked to confirm that the $55,000 reserve remains available.

What the Board Needs to Decide

The board does not need to act today, but it should know that the reserve may be needed and that the opening date now depends on the corrective actions working. If the next report shows buffer use rising faster than progress, the sponsor will bring options to the board, such as opening with temporary graphics.

Next Report

The next report, at the 81st week, will show whether the corrective actions have raised the indexes and slowed buffer use.

Conclusion

Earned value shows that the otter exhibit is about six weeks behind its plan and roughly 9% over cost on completed work. Forecasts suggest a final cost near $1.80 million and opening in April, inside the budget and buffer but with little room left. The causes are specific and the corrective actions target them, giving the sponsor a clear view of where the project stands and what is being done.

References

Fleming, Q. W., & Koppelman, J. M. (2010). Earned value project management (4th ed.). Project Management Institute.

Project Management Institute. (2019). The standard for earned value management.

Vanhoucke, M., & Vandevoorde, S. (2007). A simulation and evaluation of earned value metrics to forecast the project duration. Journal of the Operational Research Society, 58(10), 1361-1374. https://doi.org/10.1057/palgrave.jors.2602296

MGT 474 Module 7 instructions, in plain terms

Control is the work of Module 7 in Aspen's MGT 474: measuring where a project stands against its baseline and deciding what to do about any gap. Earned value is the usual tool, and a status report the usual product. Defer to your classroom's prompt for its required format; this example reports on the exhibit planned in earlier modules. Explain planned value, earned value and actual cost. Calculate schedule and cost variances and performance indexes. Forecast the estimate at completion and the finish date, noting the method used. Explain the causes behind the numbers. Recommend corrective actions with owners. Report in a form a sponsor can read quickly.

How this MGT 474 Module 7 example is built

The report covers Meadowlark Zoo's otter exhibit 73 weeks into the project, June 30, 2025. Fleming and Koppelman's book on earned value project management explains how measuring work performed against plan and cost reveals true status. The PMI standard for earned value management defines the measures. A table shows planned value $1,010,000, earned value $930,000 and actual cost $1,020,000, giving a schedule variance of minus $80,000, a cost variance of minus $90,000, an SPI of 0.92 and a CPI of 0.91. The estimate at completion is about $1.71 million. Vanhoucke and Vandevoorde's Journal of the Operational Research Society study found the earned schedule method forecast duration more reliably than earlier methods; it gives about 115 weeks. Causes include a failed concrete pour and rebar price increases. Actions include overlapping rockwork with water testing.

Reading the MGT 474 Module 7 grading rubric

Earned value reports are graded on correct calculations, accurate interpretation, sound forecasts and corrective actions that address the causes. This example defines each measure, shows every calculation in a table and interprets the indexes in plain terms. Forecasts use more than one method, and Vanhoucke and Vandevoorde's research justifies using earned schedule for time. The causes are traced to specific work packages. Corrective actions name owners and their expected effect on the forecasts, the to-complete index tests whether the base budget is still realistic and the report links cost forecasts to remaining contingency.

MGT 474 Module 7 help from the desk

Earned value papers often calculate variances correctly but stop there. Interpret what the numbers mean for the sponsor, forecast the outcome and recommend action. Another weakness is confusing earned value with actual cost; earned value is the budgeted cost of work actually completed. Show the formulas you use. Forecast duration as well as cost, and note that schedule variance in dollars loses meaning late in a project. Trace variances to causes in specific work packages. Link the forecast to contingency and reserve. Finally, keep the report short enough for a busy sponsor, with the key message first. Explain how progress was measured, since earned value is only as honest as its inputs.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official Aspen University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.

More MGT 474 and Business Administration sample papers

MGT 474 Module 7 questions, answered

What does MGT 474 Module 7 usually ask for?

Aspen's MGT 474 covers monitoring and control in this module, so an earned value status report with variances, forecasts and corrective actions is typical. Read your classroom prompt.

What is earned value?

The budgeted cost of the work actually completed by the status date, compared with planned value and actual cost to judge performance.

What do CPI and SPI mean?

The cost performance index is earned value divided by actual cost; the schedule performance index is earned value divided by planned value. Values below 1.0 indicate overruns or delays.

Where can I find a free MGT 474 Module 7 sample paper?

The example above reports a zoo exhibit's status 73 weeks into the project with earned value measures, cost and schedule forecasts and corrective actions.

How do you forecast a project's finish date with earned value?

The earned schedule method, which Vanhoucke and Vandevoorde found performed well, compares when the current earned value should have been reached with the actual time elapsed.