| Course | MGT 474 Project Management |
|---|---|
| Module | Module 5 |
| Paper type | Cost estimate and budget |
| Length | About 1,061 words, 6 pages |
| Format | APA 7 student paper |
| School | Aspen University |
| Program | Business Administration |
| Updated | October 2026 |
Free sample paper for MGT 474 Module 5
A $1.56 Million Estimate and a $1.85 Million Budget: Reference Class Forecasting for a River Otter Exhibit
Student Name
Business Administration Program, Aspen University
MGT 474: Project Management
Instructor Name
Month Day, Year
A $1.56 Million Estimate and a $1.85 Million Budget: Reference Class Forecasting for a River Otter Exhibit
Scope, work breakdown and a 106-week schedule are now in place for Meadowlark's otter habitat, the composite Kansas project this course follows. The charter set a budget of $1.85 million, a figure based on the donor's gift and early guesses. Now the zoo must show whether that budget is realistic. Last time, the lion exhibit's figure came from the board's wishes and was overrun by 40%. This paper builds a detailed estimate, sets contingency with evidence and presents the budget.
Type of Estimate
Kerzner (2017) describes estimates at different stages: order-of-magnitude estimates made early with little information, budget estimates made during planning and definitive estimates built from detailed scope, each with narrower expected accuracy. The charter's $1.85 million was an order-of-magnitude figure. With 34 work packages defined and a concept design complete, the zoo can now build a definitive estimate from the bottom up.
The Bottom-Up Estimate
Each work package was priced by the person responsible for it, using contractor quotes for construction, supplier prices for equipment and staff rates for zoo labor.
| WBS | Deliverable | Estimate |
|---|---|---|
| 1 | Project management | $95,000 |
| 2 | Design | $170,000 |
| 3 | Site and utilities | $160,000 |
| 4 | Habitat and pool | $420,000 |
| 5 | Life support systems | $265,000 |
| 6 | Holding building | $290,000 |
| 7 | Visitor experience | $120,000 |
| 8 | Animal readiness | $25,000 |
| 9 | Opening and closeout | $15,000 |
| Base estimate | $1,560,000 |
Who Estimated, and How
The project manager asked the person or firm responsible for each work package to price it, rather than estimating everything herself. The design firm priced design under its proposal. Two general contractors gave quotes for site work, the pool shell and the holding building, and the lower quote was used. The life support technician priced filtration and pumps from three suppliers. Zoo staff time for project management, animal readiness and opening was priced at loaded hourly rates. Each estimator recorded assumptions, such as the soil conditions found in the site survey, so the estimate could be checked when conditions changed.
Ranges, Not Only Points
Each estimator also gave a low and a high figure. The ranges were narrow for items with firm quotes, such as the viewing window, and wide for the pool shell and site work, where excavation could find groundwater or poor soil. Summing the high figures gives about $1.79 million, which already suggests the base estimate is optimistic. The ranges also show where uncertainty sits, guiding the risk plan in the next module.
Why Estimates Run Low
Flyvbjerg et al. (2002) examined 258 transportation infrastructure projects across 20 countries and found that costs were underestimated in 86% of them, with an average overrun of 28%. The pattern had not improved over 70 years. They concluded that technical error could not explain such consistent bias in one direction and that optimism and strategic misrepresentation, understating costs to win approval, were better explanations. A zoo exhibit is far smaller, but the same pressures exist: a donor gift sets an expected cost, and estimates drift toward it.
Reference Class Forecasting
Flyvbjerg (2006) proposed reference class forecasting as a remedy, drawing on Kahneman and Tversky's work on judgment. Instead of building the forecast only from the project's own details, the inside view, planners identify a class of similar past projects, establish the distribution of their outcomes and place the new project within it, the outside view. For the otter exhibit, the reference class is twelve exhibits with water features built at Meadowlark and three peer zoos since 2010. Their cost overruns against definitive estimates had a median of 12% and an 80th percentile of 22%.
Contingency and Reserve
Applying the reference class to the $1.56 million base gives a 50% chance of finishing under about $1.75 million and an 80% chance of finishing under about $1.90 million. The project budget will be $1.85 million, comprising the base estimate and $290,000 of contingency, about 19%, controlled by the project manager for identified risks. The board will hold a management reserve of $55,000 outside the project budget for unforeseen work, bringing total authorization to about $1.905 million, the 80th percentile.
Who Controls the Money
Contingency belongs to the project manager, who may draw on it for identified risks, such as groundwater or a supplier price increase, and must report each draw monthly with its reason. The management reserve belongs to the board and may be released only by board vote for work no one could have foreseen. Separating the two prevents contingency from being spent casually on scope additions, which the change control process from Module 3 must approve and fund separately.
Phasing and Funding
The check reveals a gap: by the end of 2025, spending reaches $1.52 million, while funding received totals $1.25 million. The zoo will bridge the gap with a short-term line of credit of up to $300,000, repaid from the final installment and campaign gifts.
| Period | Planned spending | Cumulative | Funding received |
|---|---|---|---|
| 2024 | $310,000 | $310,000 | Donor installment one, $400,000 |
| First half 2025 | $520,000 | $830,000 | Donor installment two, $400,000 |
| Second half 2025 | $690,000 | $1,520,000 | Campaign gifts, $450,000 |
| 2026 | $330,000 | $1,850,000 | Donor installment three, $400,000; campaign, $200,000 |
Comparing With the Lion Exhibit
The lion exhibit's budget of $1.86 million was set before any site survey and included no contingency line. Its overrun of $740,000 came mostly from drainage, design changes and a contractor claim. The otter exhibit's estimate includes a funded site survey, a design frozen with keeper sign-off and a contingency sized from evidence, addressing each cause directly.
Assumptions
The estimate assumes contractor prices hold through 2025, that drainage work matches the site survey and that the city's permit fees do not change. Each assumption is linked to a risk in the risk register.
Updating the Estimate
The estimate will be updated at two points: when final design is complete in October 2024 and when construction bids are signed. Each update will compare new figures with the baseline and explain differences, so the board sees how the forecast is moving long before money is spent.
Conclusion
The bottom-up estimate shows that the otter exhibit's base cost is $1.56 million, but research on cost underestimation warns that base estimates are rarely met. Reference class forecasting sets contingency from evidence rather than hope, and the budget, reserve and funding plan together give the board an honest picture of what the exhibit is likely to cost.
References
Flyvbjerg, B. (2006). From Nobel Prize to project management: Getting risks right. Project Management Journal, 37(3), 5-15. https://doi.org/10.1177/875697280603700302
Flyvbjerg, B., Holm, M. S., & Buhl, S. (2002). Underestimating costs in public works projects: Error or lie? Journal of the American Planning Association, 68(3), 279-295. https://doi.org/10.1080/01944360208976273
Kerzner, H. (2017). Project management: A systems approach to planning, scheduling, and controlling (12th ed.). Wiley.
MGT 474 Module 5 instructions, in plain terms
Module 5 in Aspen's MGT 474 is where a project acquires a price. Expect to estimate costs from the work breakdown, explain how much uncertainty the estimate carries and present a budget the sponsor can approve. Your classroom's Module 5 wording takes priority over this example, which prices the exhibit planned in earlier modules. Explain the type of estimate and its basis. Build the estimate from work packages or deliverables. Use research to explain why estimates tend to run low. Set contingency with a method you can defend, such as data from similar projects. Separate contingency from management reserve, and say who may release each. Phase the budget over time and check it against funding, noting any months when spending runs ahead of cash.
How the MGT 474 Module 5 example is put together
Pricing comes next for the otter exhibit. Kerzner's textbook distinguishes order-of-magnitude, budget and definitive estimates; this is a definitive estimate built from the 34 work packages. A table totals $1.56 million across nine deliverables, from $15,000 for opening to $420,000 for the habitat and pool. Flyvbjerg, Holm and Buhl's Journal of the American Planning Association study of 258 transport projects found costs underestimated in 86% of them. Flyvbjerg's Project Management Journal article explains reference class forecasting. Using twelve exhibits at four zoos, the median overrun was 12% and the 80th percentile 22%, so the zoo sets contingency at $290,000 inside the $1.85 million budget and a $55,000 management reserve outside it. A quarterly spending plan is checked against donor installments.
Reading the MGT 474 Module 5 grading rubric
Budget papers are judged on estimates tied to the work breakdown, a defensible basis for contingency, a clear distinction between contingency and reserve and a check that money will be available when needed. This example builds the estimate from deliverables and shows the total. Flyvbjerg, Holm and Buhl's study explains why base estimates run low, and reference class forecasting turns that knowledge into a number. The budget table and reserve show who controls which money. The cash flow check catches a timing gap before it becomes a crisis, and the paper states who controls each pool of money.
Common MGT 474 Module 5 mistakes, and how to avoid them
Budget papers often add a flat 10% contingency without explaining why. Base contingency on evidence, such as how similar projects performed. Another weakness is an estimate that does not match the work breakdown; build from deliverables or work packages so nothing is missed. Distinguish contingency, used by the project manager for identified risks, from management reserve, held by the sponsor for the unforeseen. Phase the budget over time and compare it with funding. State the estimate type and its accuracy. Finally, record the assumptions behind the estimate, since they will be tested during the project. Ask estimators for ranges as well as single figures.
Write yours, or have the desk draft it
This paper is an original model document written by our desk, not a submitted student paper and not an official Aspen University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.
More MGT 474 and Business Administration sample papers
- MGT 474 Module 1: Projects, Life Cycles and Success
- MGT 474 Module 2: Project Selection and the Charter
- MGT 474 Module 3: Scope and the Work Breakdown Structure
- MGT 474 Module 4: Scheduling and the Critical Path
- MGT 474 Module 6: Project Risk Management
- MGT 474 Module 7: Monitoring With Earned Value
- MGT 474 Module 8: Project Closing and Lessons Learned
- MGT 494 Module 8: Comprehensive Strategic Case
- BUS 484 Module 2: Opportunity Assessment
- MGT 424 Module 2: Traits and Skills of Leaders
- BUS 225 Module 3: Contract Formation and Breach
MGT 474 Module 5 questions, answered
What does MGT 474 Module 5 usually ask for?
Aspen's MGT 474 covers cost estimating and budgeting in this module, so building an estimate from the work breakdown and setting a budget with contingency is typical. Read your classroom prompt.
Why do projects run over budget?
Flyvbjerg, Holm and Buhl found costs underestimated in 86% of the transport projects they studied and argued that optimism and strategic misrepresentation explain the pattern better than honest error.
What is reference class forecasting?
A method, drawn from Kahneman and Tversky's work and applied by Flyvbjerg, that forecasts a project's outcome from the actual results of similar past projects.
Where can I find a free MGT 474 Module 5 sample paper?
The example above estimates a zoo exhibit at $1.56 million from its work breakdown and sets contingency and reserve with reference class forecasting.
What is the difference between contingency and management reserve?
Contingency covers risks already named and is spent by the project manager; reserve sits with the sponsor and covers what nobody foresaw.