MGT 474 Module 8 Project Closing and Lessons Learned Example

Reviewed by Douglas Renshaw, MBA Aspen University Updated October 2026

This MGT 474 Module 8 sample paper closes the composite Wichita zoo's river otter exhibit, followed through the whole course, which opened on May 21, 2026, four days before Memorial Day, at a final cost of $1.81 million against a $1.85 million budget. Aspen University's Project Management course ends with closing, when results are measured, contracts settled and lessons captured. The exhibit met every acceptance criterion, used 14 of its 15 buffer weeks and drew $250,000 of its $290,000 contingency. Its first summer brought 14,000 more visitors than the same months the year before. The PMBOK Guide frames closing around the value delivered. Williams found that organizations collect lessons but rarely act on them, and Keegan and Turner showed time pressure crowds out learning. A table turns each lesson into a change in the zoo's standard project process.

CourseMGT 474 Project Management
ModuleModule 8
Paper typeProject closeout report
LengthAbout 1,071 words, 6 pages
FormatAPA 7 student paper
SchoolAspen University
ProgramBusiness Administration
UpdatedOctober 2026

Free sample paper for MGT 474 Module 8

1

Open Four Days Early and $40,000 Under: A Closeout Report and Lessons Learned for a River Otter Exhibit

Student Name

Business Administration Program, Aspen University

MGT 474: Project Management

Instructor Name

Month Day, Year

What this page is doingThe title states the project's result against its two main constraints. APA 7 student title page.
2

Open Four Days Early and $40,000 Under: A Closeout Report and Lessons Learned for a River Otter Exhibit

On May 21, 2026, four days before Memorial Day, the new otter habitat at Meadowlark, a composite Wichita institution, welcomed its first visitors. Two otters from a partner zoo had completed quarantine and training, the water had passed thirty days of testing and the donor cut the ribbon. This report closes the project: it compares results with the baseline, reports early benefits, completes administrative closure and records lessons for the zoo's next project.

Results Against the Baseline

ElementBaselineActual
ScopeNine deliverables, 34 work packagesAll nine accepted; one approved change, a keeper access tunnel added in design
OpeningBy Memorial Day 2026May 21, 2026
Buffer15 weeksAbout 14 weeks used
Base budget$1,560,000$1,560,000 of base work plus overrun on pool and rockwork
Contingency$290,000$250,000 used
Total cost$1,850,000 budget$1,810,000
Management reserve$55,000 held by boardNot used
Acceptance criteriaWater, window, keeper and standards testsAll met
What this page is doingThe lion exhibit ran seven months late and 40% over; the otter exhibit opened on time and under budget, though with less than a week of buffer to spare.
3

Where the Buffer Went

The corrective actions after the 73rd week recovered about three weeks, but two later events consumed more. The first water tests failed on bacterial counts, and the veterinarian required a second thirty-day series after the ultraviolet sterilizer was replaced under warranty. Then one otter developed a minor skin infection during quarantine, extending quarantine by three weeks. Neither event was a surprise in kind: both appeared in the risk register, and the buffer existed for exactly such events. Without it, the exhibit would have opened in late June.

Early Benefits

The charter set benefit goals as well as cost and time. From the opening through August, attendance was 14,000 higher than in the same months of 2025, on track for the 25,000-visitor annual goal. The campaign raised $680,000 against a $650,000 target. The education team reports that the underwater window has become the most photographed spot in the zoo. Full benefits will be reviewed after a year of operation.

Closing the Project

The PMBOK Guide emphasizes that projects exist to deliver value and that closing includes transitioning outcomes to the people who will sustain them (Project Management Institute, 2021). Administrative closure for the exhibit included final payment to the contractor after the punch list was completed, closing the line of credit, filing permits and inspection records, archiving design documents and the risk register and confirming warranties: one year on construction, three on pumps and filters and ten on the viewing window. Handover to operations included life support manuals, a maintenance schedule, keeper training records and spare parts for filters and ultraviolet lamps. The life support technician signed for the systems on June 15.

Why Lessons Are Usually Lost

Williams (2008) surveyed project management practitioners about lessons-learned practices and found that while most organizations held some form of post-project review, few respondents were satisfied with how lessons were then used. Lessons were captured in reports that were rarely read and seldom changed later behavior. He argued that lessons are more likely to transfer when they are explained through causal stories and built into organizational processes. Keegan and Turner (2001) studied learning in project-based firms and found that time pressure and the move to the next project pushed learning aside, and that firms often relied on the number of reviews held rather than on whether learning changed practice. The lion exhibit's lessons were never written down, which helps explain why its problems were nearly repeated until the board intervened.

Lessons as Changes

LessonEvidenceChange to the zoo's project standardOwner
Involve animal care before designOne design change, against many on the lion exhibitKeeper and veterinarian sign-off required before final designCurator of mammals
Survey the site before budgetingGroundwater anticipated and fundedSite survey funded in every capital project charterFacilities manager
Set contingency from evidence$250,000 used of $290,000Reference class data kept and updated after each projectChief financial officer
Report earned schedule monthlyDelay caught 73 weeks into the project with time to recoverMonthly earned value and buffer report to sponsorProject manager
Avoid cold-weather concrete poursFailed pour cost three weeksTemperature rule in all construction contractsFacilities manager
Make uncomfortable risks speakableDonor timing risk resolved earlyAnonymous risk cards at every risk reviewSponsor

What Went Less Well

A closeout report that lists only successes teaches little. Three things went less well. Cold-weather concrete cost three weeks and $40,000, a risk the contractor should have managed and the zoo should have written into the contract. The rockwork subcontractor's productivity was estimated from flat walls, not curved pool edges, a lesson for future estimates. And the buffer, while it protected the opening, was nearly exhausted; a second unexpected event would have delayed the opening. The team also found that the anonymous risk cards became routine by the final months, with fewer real concerns raised, suggesting the practice needs refreshing on long projects.

Celebrating the Team

Closing also recognizes the people who did the work. The board hosted a dinner for the project team, contractors and keepers, and the donor's recognition wall lists every team member by name, a small step that Keegan and Turner's emphasis on learning cultures would endorse.

Keeping the Lessons Alive

Following Williams's advice, the project manager will present the story of the exhibit, including the failed pour and how the delay was recovered, to the next project team at its kickoff. The zoo's project standard, a twelve-page document, has been updated with the six changes, and the deputy director will check at the next charter approval that they are used.

Final Accounts

The final cost of $1.81 million comprised $1.56 million of base work, $85,000 for dewatering, $70,000 for the concrete repour and steel prices, $55,000 for rockwork productivity and $40,000 for water system retesting and extra quarantine care. All were paid from contingency, leaving $40,000 unspent, which the board returned to the zoo's capital fund.

Conclusion

The otter exhibit met its scope, opened early and finished under budget, and its first summer suggests the benefits will follow. The comparison with the lion exhibit shows the value of the practices followed through this course: a charter with authority, a protected scope, a buffered schedule, an evidence-based budget, a living risk register and earned value control. Turning lessons into changes in the zoo's standard process gives the next project the best chance to benefit from them.

References

Keegan, A., & Turner, J. R. (2001). Quantity versus quality in project-based learning practices. Management Learning, 32(1), 77-98. https://doi.org/10.1177/1350507601321006

Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK guide) (7th ed.).

Williams, T. (2008). How do organizations learn lessons from projects, and do they? IEEE Transactions on Engineering Management, 55(2), 248-266. https://doi.org/10.1109/TEM.2007.912920

MGT 474 Module 8 instructions, in plain terms

The closing module of Aspen's MGT 474 asks for an honest account of how a project ended: results against the baseline, the administrative work of shutting it down and the lessons worth keeping. The prompt in your classroom sets the required sections; this example closes the project followed through earlier modules. Compare final scope, schedule and cost with the baseline. Report early evidence on benefits. Describe administrative closure, including contracts, accounts, records and handover to operations. Use research on organizational learning to explain how lessons will be kept. Record lessons as specific changes to how future projects will be run, with owners.

Inside the MGT 474 Module 8 example

The report covers Meadowlark Zoo's otter exhibit, which opened May 21, 2026. A table compares baseline and actual results: all nine deliverables accepted, opening four days ahead of the deadline, final cost $1.81 million and $250,000 of contingency used. The PMBOK Guide's seventh edition emphasizes delivering value and transitioning results to operations. Williams's IEEE Transactions on Engineering Management survey found most organizations held lessons-learned reviews but few were satisfied with how lessons were used. Keegan and Turner's Management Learning study found that time pressure and the move to new projects pushed learning aside. A table lists six lessons, such as keeper involvement before design and earned schedule reporting, each turned into a change in the zoo's project standard with an owner. Handover covers warranties, life support manuals and keeper training records.

Reading the MGT 474 Module 8 grading rubric

Closeout reports are judged on honest comparison with the baseline, attention to benefits as well as outputs, complete administrative closure and lessons turned into changes rather than lists. This example compares every baseline element with results. Early attendance evidence addresses benefits. Williams's and Keegan and Turner's research explains why lessons are usually lost, and the report responds by embedding lessons in the zoo's standard process with owners. The handover section shows the project ending cleanly, and the report is candid about what went less well, including how close the buffer came to running out. The paper ties back to Modules 1 through 7.

MGT 474 Module 8 help: mistakes that cost marks

Closeout papers often list lessons learned that are too vague to change anything, such as communicate better. Write each lesson as a specific change to how the next project will be run, with an owner. Another weakness is judging success only by time and budget; report on scope acceptance and early benefits. Compare actual results with the baseline numerically, and explain where buffer and contingency went. Include administrative closure: contracts, final accounts, records, warranties and handover. Use research on why organizations fail to learn from projects. Acknowledge what went wrong as well as right. Finally, connect the closeout to earlier planning documents, showing how the plan performed.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official Aspen University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.

More MGT 474 and Business Administration sample papers

MGT 474 Module 8 questions, answered

What does MGT 474 Module 8 usually ask for?

Aspen's MGT 474 ends with project closing, so a closeout report comparing results with the baseline and recording lessons learned is typical. Check your classroom prompt.

What happens when a project closes?

Deliverables are accepted, contracts and accounts are closed, records are archived, results are handed over to operations and lessons are captured.

Do organizations learn from lessons-learned reviews?

Often not. Williams found many organizations conduct reviews but are dissatisfied with how lessons are used afterward.

Where can I find a free MGT 474 Module 8 sample paper?

The complete report above closes a zoo's river otter exhibit, comparing results with the baseline and turning lessons into process changes.

How can lessons learned be made to stick?

By turning each lesson into a change in standard processes or templates, assigning an owner and checking that the next project uses it.