MGT 474 Module 4 Scheduling and the Critical Path Example

Reviewed by Douglas Renshaw, MBA Aspen University Updated October 2026

This MGT 474 Module 4 sample paper schedules the composite Wichita zoo's river otter exhibit, scoped in Module 3, using sixteen activities and the critical path method. Aspen University's Project Management course teaches how to find the sequence of work that sets a project's length, and an exhibit that ends with live animals needing quarantine and training has a long one. A forward and backward pass shows a 106-week critical path running from concept design through permits, construction, life support, water testing and animal training. Kelley and Walker's original method explains the calculation. Buehler, Griffin and Ross's planning fallacy explains why the estimates are probably optimistic. Goldratt's critical chain suggests protecting the deadline with a shared buffer rather than padding each task. A table of activities with float and a 15-week project buffer before Memorial Day 2026 complete the schedule.

CourseMGT 474 Project Management
ModuleModule 4
Paper typeSchedule and critical path analysis
LengthAbout 1,062 words, 6 pages
FormatAPA 7 student paper
SchoolAspen University
ProgramBusiness Administration
UpdatedOctober 2026

Free sample paper for MGT 474 Module 4

1

One Hundred Six Weeks on the Critical Path: Scheduling a River Otter Exhibit With a Buffer for the Planning Fallacy

Student Name

Business Administration Program, Aspen University

MGT 474: Project Management

Instructor Name

Month Day, Year

What this page is doingThe title states the critical path length and the bias the buffer guards against. APA 7 student title page.
2

One Hundred Six Weeks on the Critical Path: Scheduling a River Otter Exhibit With a Buffer for the Planning Fallacy

With scope settled and 34 work packages defined, the otter exhibit at Meadowlark, a composite zoo in Wichita, Kansas, now needs a timetable. The next step is a schedule that shows whether the exhibit can open by Memorial Day 2026 and which activities control that date. Planning begins in February 2024, after the board approved the charter. This paper builds the schedule using the critical path method.

The Method

Kelley and Walker (1959) introduced the critical path method to plan and schedule large engineering projects. Their method treats a project as a network of activities joined by dependencies, each with a duration. A forward pass through the network yields every activity's earliest possible dates; a backward pass from the finish yields the latest dates that still protect the end date. Activities whose early and late dates are equal form the critical path, and any delay to them delays the project. Other activities have float.

Activities, Durations and Float

Durations are in weeks, estimated by the project manager with the designer, contractor and animal care staff. Counting starts at zero on February 1, 2024.

ActivityWeeksPredecessorsEarly startLate startFloat
A Concept design12None000
B Site survey6None066
C Final design24A, B12120
D Permits16C36360
E Contractor bid and award12C36404
F Site preparation and drainage8D, E52520
G Pool shell16F60600
H Life support installation12G76760
I Holding building18F607616
J Viewing window6G76826
K Rockwork and plantings8H, J88946
L Graphics design and fabrication20C368246
M Graphics installation2K, L961026
N Water testing6H, J88880
O Otter arrival, quarantine and training10N, I94940
P Opening preparation2O, M1041040
What this page is doingThe otters cannot arrive until the water passes testing, and the water cannot be tested until the life support is running; the zoo's schedule is set by plumbing and biology.
3

Building the Network

The activities come from the work breakdown structure's work packages, grouped where packages are always done together. Dependencies were checked with the contractor and keepers. Two were easy to miss: the viewing window must be set before rockwork surrounds it, and water testing cannot begin until both the life support and the window are in place, since the window forms part of the pool wall.

The Critical Path

The critical path runs A, C, D, F, G, H, N, O, P: concept design, final design, permits, site preparation, pool shell, life support, water testing, otter training and opening preparation, totaling 106 weeks. The project can finish in mid-February 2026 at the earliest. Graphics, with 46 weeks of float, can wait; the holding building has 16 weeks. Permits deserve special attention: they are on the critical path, and their duration depends on the city, not the zoo.

Why Estimates Run Short

Buehler et al. (1994) studied what they called the planning fallacy: people predict that their own tasks will be finished sooner than they are, even when they know that similar past tasks ran late. In their studies, students' predictions of when they would finish academic projects were markedly optimistic, and most finished later than their own predictions. People focus on plans for the task at hand and set aside the lessons of past experience. The lion exhibit's schedule showed the same pattern: every phase ran longer than planned.

Protecting the Deadline

Goldratt (1997) argued in his business novel on critical chain that individual estimates are usually padded for safety, yet projects still run late, because padding is consumed by delayed starts and work that expands to fill the time. He proposed estimating tasks without hidden padding and placing the protection in a shared project buffer at the end, with smaller feeding buffers where noncritical paths join the critical one. The otter exhibit's schedule finishes 15 weeks before Memorial Day 2026; those 15 weeks are the project buffer. The holding building's 16 weeks of float and the graphics' float act as feeding buffers.

Where the Estimates Came From

Each duration was estimated by the people who will do the work, then checked against the lion exhibit's actual durations. Final design was first estimated at 18 weeks; the lion exhibit's design took 27, so the estimate was raised to 24. Permits were estimated at 10 weeks by the designer but 16 by the zoo's city liaison, who remembered that the lion exhibit's permits required two rounds of review; the schedule uses 16. Using the zoo's own history in this way is a partial guard against the planning fallacy, since it puts past experience in front of the people estimating.

What Could Shorten the Path

Three options could shorten the critical path if needed. Permits could be split, with site preparation permitted before the full building permit. The holding building and pool shell could be bid together to save part of the contractor award time. And otter training could begin in temporary holding while water testing finishes, if the veterinarian agrees. Each option carries risks and costs and would be used only if the buffer runs low.

Resource Conflicts

The schedule assumes the zoo's life support technician can oversee filtration installation in weeks 76 to 88. That period overlaps with the annual maintenance shutdown of the aquarium building, which the technician also leads. The project manager has asked operations to move the shutdown to the following winter, a reminder that critical path schedules assume resources are available when the activities need them.

Monitoring the Schedule

The project manager will report monthly on critical path progress and on how much of the buffer has been used compared with how much of the work is complete. If more than a third of the buffer is used before construction starts, the sponsor will review options, such as applying for permits in phases.

Conclusion

The critical path method shows that the otter exhibit's length is set by a chain from design through permits, construction, life support, water testing and animal training. Research on the planning fallacy suggests the estimates are optimistic, and Goldratt's critical chain shows how to protect the opening with a visible 15-week buffer rather than hidden padding.

References

Buehler, R., Griffin, D., & Ross, M. (1994). Exploring the "planning fallacy": Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366-381. https://doi.org/10.1037/0022-3514.67.3.366

Goldratt, E. M. (1997). Critical chain. North River Press.

Kelley, J. E., Jr., & Walker, M. R. (1959). Critical-path planning and scheduling. In Papers presented at the December 1-3, 1959, Eastern Joint IRE-AIEE-ACM Computer Conference (pp. 160-173). Association for Computing Machinery. https://doi.org/10.1145/1460299.1460318

Reading the MGT 474 Module 4 assignment instructions

Time is the subject of Module 4 in Aspen's MGT 474. Students turn work packages into a dated network, find the chain of activities that fixes the finish date and say how that date will be defended. Work from your classroom's Module 4 instructions; the example schedules the project scoped earlier. List activities with durations and dependencies, drawn from the work breakdown structure. Calculate early and late start and finish dates with a forward and backward pass. Identify the critical path and the float on other activities. Explain why duration estimates tend to be optimistic. Describe how the schedule will protect the deadline, for example with buffers, and say how progress against it will be tracked.

Inside the MGT 474 Module 4 example

Here the otter exhibit gets its timetable, starting February 2024. A table lists sixteen activities, such as final design at 24 weeks, permits at 16 and life support installation at 12, with their predecessors, early and late starts and float. The forward pass gives a project length of 106 weeks; the critical path runs through concept design, final design, permits, site preparation, pool shell, life support, water testing, animal training and opening preparation. Graphics have 46 weeks of float and the holding building 16. Kelley and Walker's paper on critical-path planning describes the method. Buehler, Griffin and Ross showed in a series of studies that people expect to finish their own tasks sooner than they do. Goldratt's book on critical chain proposes pooled buffers. The schedule finishes in February 2026, leaving a 15-week buffer before Memorial Day.

MGT 474 Module 4 rubric: what earns full marks

Scheduling papers are graded on correct forward and backward pass calculations, accurate identification of the critical path and float, attention to estimating bias and a sensible way to protect the deadline. This example shows every activity's dates and float in one table, so the calculations can be checked. The critical path is traced and explained in terms of the work. Buehler, Griffin and Ross's research supports the buffer, and Goldratt's critical chain explains why one shared buffer beats padding each task. Monitoring focuses on the critical path and buffer use.

Common MGT 474 Module 4 mistakes, and how to avoid them

Scheduling papers often present a Gantt chart without showing how the critical path was found. Show the forward and backward pass, even in a table. Another weakness is an activity list invented from scratch; activities should come straight from the work packages already defined. Check dependencies carefully, since one missing link changes the critical path. Calculate float and explain what it means for managers. Address estimating optimism with research. Protect the deadline with a visible buffer rather than hidden padding. Finally, describe how you will watch the critical path and buffer during the project. Check whether the people and equipment the schedule assumes will be free.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official Aspen University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.

More MGT 474 and Business Administration sample papers

MGT 474 Module 4 questions, answered

What does MGT 474 Module 4 usually ask for?

Aspen's MGT 474 covers scheduling in this module, so building a schedule, finding the critical path and discussing schedule risk is typical. Look at your classroom prompt.

What is the critical path?

The longest sequence of dependent activities through a project, which determines the shortest possible project duration; activities on it have zero float.

What is float?

The amount of time an activity can be delayed without delaying the project, found by comparing its early and late dates.

Where can I find a free MGT 474 Module 4 sample paper?

The example above schedules a zoo's river otter exhibit with sixteen activities, a 106-week critical path and a 15-week project buffer.

What is the planning fallacy?

The label Buehler, Griffin and Ross gave to a stubborn optimism about one's own deadlines, which persists even in people who remember past tasks running over.