MGT 645 Module 6 Project Work and Delivery Example

Reviewed by Douglas Renshaw, MBA Aspen University Updated October 2026

This MGT 645 Module 6 sample paper turns the approved plan for a composite pizza plant's allergen-safe product line into execution and delivery: managing contractors and vendors, building quality into the work, deciding issues quickly during installation and handing a certified line to operations. Aspen University's MBA project management specialization treats project work and delivery as two performance domains, the first about doing the work and the second about producing outcomes that create value. Turner and Müller described projects as temporary organizations with their own governance. Ahola and colleagues reviewed what project governance means, from rules inside a project to the wider organization's control of it. Atkinson argued that success criteria must reach beyond cost, time and quality. A table assigns delivery activities, owners and acceptance criteria, and a governance structure speeds decisions during start-up.

CourseMGT 645 Project Management Essentials
ModuleModule 6
Paper typeMBA execution and delivery paper
LengthAbout 1,032 words, 6 pages
FormatAPA 7 student paper
SchoolAspen University
ProgramMaster of Business Administration
UpdatedOctober 2026

Free sample paper for MGT 645 Module 6

1

From Contracts to the First Certified Pizza: Executing and Delivering a Gluten-Free Line as a Temporary Organization

Student Name

Master of Business Administration, Aspen University

MGT 645: Project Management Essentials

Instructor Name

Month Day, Year

What this page is doingThe title traces delivery from contracts to the first certified product. APA 7 student title page.
2

From Contracts to the First Certified Pizza: Executing and Delivering a Gluten-Free Line as a Temporary Organization

With its plan approved, the gluten-free room at the Eau Claire pizza plant moves into execution. Over the next twelve months, a general contractor will build the walled room and air handling, an equipment vendor will supply and install the line, the plant's maintenance crew will connect utilities and the product team will finish recipes, packaging and procedures. Then the line must be started, certified and handed to operations. This paper plans the execution and delivery.

The Project as a Temporary Organization

Turner and Müller (2003) argued that a project is best understood as a temporary organization to which resources are assigned to deliver beneficial change. Like any organization, it needs structures, roles and decision rules; unlike the permanent organization, it ends when its work is done. The gluten-free project draws people and money from the plant for a limited time, coordinates outside firms and must hand its results back to the permanent organization at the end.

Governance

Ahola et al. (2014) reviewed the literature on project governance and found two main meanings. Governance can refer to the structures and processes within a project, such as decision rights and reporting, or to the parent organization's governance of its projects, such as portfolio decisions and oversight. Both matter. Within the project, decisions during installation must be fast. From the company's side, the board needs oversight without slowing work. The authors also noted that the two views often meet at the sponsor, who sits in both the temporary and the permanent organization. Here the chief operating officer chairs the steering group and reports to the board each quarter, which gives one channel for oversight instead of several competing ones.

DeliveryOwnerAcceptance criteria
Walled room and air handlingGeneral contractor; project managerPositive air pressure held for 72 hours; inspector sign-off
Production equipmentEquipment vendor; process engineerRuns at rated speed for two full shifts
RecipesResearch and development bakerFinal tasting panel score of 4 of 5; locked by month 11
PackagingSales account managerRetailer approval; label review by advocacy group
Procedures and trainingFood safety coordinatorAll line workers trained and observed
CertificationQuality managerThree consecutive clean swab rounds; certificate issued
HandoverProject manager; plant managerOperations accepts line; benefits tracker assigned
What this page is doingThe project is done when the plant manager signs for a certified line, not when the vendor's crew drives away.
3

Decision Rights in Execution

During installation and start-up, problems arise hourly. A daily start-up meeting of the project manager, process engineer, quality manager and vendor lead will decide issues under $25,000 on the spot. Larger issues go to a steering group of the sponsor, plant manager and sales vice president, which meets weekly and can convene within a day.

Procurement and Relationships

Contracts with the general contractor and equipment vendor are fixed-price with clear specifications. But fixed-price contracts can encourage vendors to resist changes, so the project manager will meet the vendor lead weekly and share the start-up schedule openly, treating the vendor as part of the temporary organization.

Building Quality In

Quality checks occur during work, not only at the end: air pressure is tested before walls are sealed, swabs are taken during trial runs and procedures are tested on the mock-up before the room opens. The certification body is invited to a preliminary walk-through in month ten, two months before the formal audit, so that any finding about room layout or cleaning procedures can be corrected while contractors are still on site. Defects found after the contractor leaves cost more and take longer.

Why Execution Fails

Pinto and Mantel (1990) studied how project failure is perceived and what causes it, and found that the causes differ by project type and by whether failure is judged on internal efficiency or on client satisfaction. Their results warn against a single checklist. For a construction and equipment project, technical tasks and troubleshooting weighed heavily; for client satisfaction, consultation with the client and acceptance mattered more. The gluten-free line has both sides: an engineering build and retail customers who must accept the product. The plan therefore pairs technical troubleshooting capacity during start-up with regular reviews of samples by the two retail buyers.

Handling Changes

Changes during execution are logged, sized and routed by the same thresholds that govern decisions. A request from a retailer to add a fourth crust size, for example, would go to the steering group because it touches equipment settings, packaging and the certified procedures. The project manager reports open changes, decisions made and their effect on the ship date in a one-page weekly note to the sponsor and plant manager.

Start-Up as the Hardest Stretch

The history check in Module 5 showed that the plant's past projects slipped mainly during start-up. Execution planning concentrates people there: the vendor's technician stays on site for six weeks instead of two, a second shift of trained operators is available for trial runs and the research baker is released from other launches until the recipes run cleanly at speed.

Success Beyond the Iron Triangle

Atkinson (1999) argued that project management had relied too heavily on cost, time and quality as success criteria and proposed including benefits to the organization and to stakeholder communities. The handover plan therefore includes a benefits tracker owned by the vice president of sales: retail listings, sales and repeat orders over three years.

The Handover

Handover is planned as a stage of its own, not a date. For four weeks after certification the project team and the plant's operations crew run the line together. Operators take over one shift at a time, the food safety coordinator observes each crew through a full cleaning cycle and maintenance receives the vendor's manuals, spare parts list and preventive schedule. The plant manager signs acceptance only after the line has run two weeks under operations alone with clean swabs. The project then closes, its people return to their departments and a short review records what the next plant project should copy or avoid.

Conclusion

Turner and Müller's temporary organization, Ahola and colleagues' governance and Atkinson's broader success criteria shape an execution plan with fast decisions, quality built in and a handover that ends with a certified line and someone accountable for the benefits.

References

Ahola, T., Ruuska, I., Artto, K., & Kujala, J. (2014). What is project governance and what are its origins? International Journal of Project Management, 32(8), 1321-1332. https://doi.org/10.1016/j.ijproman.2013.09.005

Atkinson, R. (1999). Project management: Cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria. International Journal of Project Management, 17(6), 337-342. https://doi.org/10.1016/S0263-7863(98)00069-6

Pinto, J. K., & Mantel, S. J., Jr. (1990). The causes of project failure. IEEE Transactions on Engineering Management, 37(4), 269-276. https://doi.org/10.1109/17.62322

Turner, J. R., & Müller, R. (2003). On the nature of the project as a temporary organization. International Journal of Project Management, 21(1), 1-8. https://doi.org/10.1016/S0263-7863(02)00020-0

Reading the MGT 645 Module 6 assignment instructions

Module 6 of Aspen's MGT 645 covers project work and delivery: how the work is carried out, procured and governed, and how outputs are accepted and turned into benefits. A paper usually plans execution for a specific project. Use your section's Module 6 instructions; the example executes the gluten-free line planned earlier. Explain the project as a temporary organization with its own governance. Set decision rights and escalation for execution. Plan procurement and quality activities. Define deliverables and acceptance criteria. Plan the handover to operations and how benefits will be tracked. Show how changes requested during execution are sized and approved, and support your choices with project management research cited in APA 7 form.

How this MGT 645 Module 6 example is built

Execution involves a general contractor for the room, an equipment vendor and its installers, the plant's maintenance crew and the product team. Turner and Müller's International Journal of Project Management article frames projects as temporary organizations to which resources are assigned to deliver change. Ahola and colleagues' review in the same journal distinguishes governance internal to a project from governance of projects by the parent organization. Atkinson's article argues that cost, time and quality are only part of success and that benefits to the organization and stakeholders must count. A table lists deliveries, such as the room passing air pressure tests and three clean swab rounds, with owners and acceptance criteria. Governance includes a daily start-up meeting with authority to decide issues under $25,000 and a steering group for larger ones. The handover includes trained crews, procedures and a benefits tracker.

MGT 645 Module 6 rubric: what earns full marks

Execution papers show their quality in how clearly they define who decides, what counts as done and how the result passes to the people who will run it. This example treats the project as a temporary organization, following Turner and Müller, and builds governance to match. Ahola and colleagues' review clarifies the difference between project-level and organizational governance. Atkinson's argument shapes acceptance criteria that include benefits. The table makes delivery concrete, and the handover plan closes the gap between output and value. A strong submission also matches the decision thresholds to the risks found during planning and concentrates people where history says delays happen, which here means start-up rather than construction.

MGT 645 Module 6 help from the desk

Execution papers often describe doing the plan without addressing governance, acceptance or handover. Define who decides what during execution, especially when problems arise quickly. Another weakness is accepting deliverables on cost and schedule alone; set acceptance criteria tied to quality and benefits. Plan procurement relationships, not only contracts. Build quality into the work rather than inspecting it at the end. Plan the handover to operations, including training and documentation. Finally, assign someone to track benefits after the project closes. Keep the change process simple enough that people use it under pressure, and describe how status reaches the sponsor each week.

Write yours, or have the desk draft it

This paper is an original model document written by our desk, not a submitted student paper and not an official Aspen University document. Read it for the moves, then write your own to the instructions in your classroom. If you want one built to your exact prompt and rubric, the first custom sample is free and arrives in 24 to 48 hours.

More MGT 645 and Master of Business Administration sample papers

MGT 645 Module 6 questions, answered

What does MGT 645 Module 6 usually ask for?

Aspen's MGT 645 covers project work and delivery in this module, so an MBA paper on executing a project and delivering accepted outcomes is typical. Look at your classroom prompt.

What is a temporary organization?

Turner and Müller's view of a project as an organization created to deliver a change, to which resources are assigned for a limited time.

What is project governance?

Ahola and colleagues distinguish governance within a project, its structures and decision rules, from governance of projects by the parent organization.

Where can I find a free MGT 645 Module 6 sample paper?

The example above plans execution, governance, acceptance and handover for a gluten-free production line.

Is cost, time and quality enough to judge a project?

Atkinson argued it is not; benefits to the organization and stakeholders should also count as success criteria.